Design and labels
The manifold, loops and zone labels match the approved design and as-installed layout.
Currently closed
Professional commissioning guide
Commissioning proves that the system is filled, purged, leak-free, responding to its controls and delivering the design flow through every circuit.
It is more than connecting a hose to the manifold. Use the project design, current product instructions and heat-source requirements.
Commissioning should be completed by a competent heating professional using the Uheat design, current product instructions and heat-source requirements. Electrical wiring and testing must be completed by a suitably qualified electrician.
Before commissioning begins
The manifold, loops and zone labels match the approved design and as-installed layout.
Required pressure tests were completed and recorded at the correct installation stages.
Screed, levellers, adhesives and finishes have cured or dried for the specified period.
The heat source, mixing control, pump, wiring centre, thermostats and actuators are installed.
Protective devices and control wiring have been tested by the responsible electrician.
Flow rates, circuit schedule and permitted temperature settings are available at the manifold.
Seven stages
Work in order and record each result rather than adjusting the system by feel.
Check manifold orientation, valves, fill and drain points, vents, pump or mixing assembly, actuators and labels. Record approved site changes.
Use the separate filling guide. Purge one circuit at a time until water runs without visible air, then restore the correct valve positions.
Set the cold pressure required by the design and heat-source instructions, inspect accessible joints and record the stable result.
Call for heat from each thermostat. Confirm the right actuator, pump and heat-source demand operate, then close correctly when demand ends.
Configure the heat source, mixing arrangement and pump to the design values. Confirm flow direction and investigate persistent air noise.
With the relevant zones open, adjust every flowmeter to its design rate. Recheck all loops after changes and record final flow.
Follow the screed and finish start-up schedule, raise temperature gradually where instructed and prove every zone through a normal cycle.
Starting too early or raising temperature too quickly can damage screed, adhesives or finishes. Cure, moisture and first-heat requirements come from the relevant material manufacturers.
Commissioning record
The handover should show what was designed, tested, set and changed.
| Record | Minimum information |
|---|---|
| Project and system | Address or area, heat source, manifold ID, commissioning date and responsible person. |
| Circuit schedule | Zone or room, loop number, design flow, final measured flow and actuator channel. |
| Temperatures | Relevant flow, return, mixing and configured maximum values after stable operation. |
| Pressure | Cold fill pressure, available test information and final stable operating pressure. |
| Controls | Thermostat names, sensor or limit settings, schedules, wiring-centre outputs and interlock result. |
| Pump and mixing | Pump mode, mixing setting and any design-specific differential or bypass setting. |
| Floor start-up | Cure confirmation, start date, staged temperatures and observations. |
| Exceptions | Approved changes, unresolved defects, restricted zones and actions before handover. |
Area, heat source, manifold ID, date and responsible person.
Zone, loop, design and final flow, and actuator channel.
Flow, return, mixing and maximum values after stable operation.
Cold fill, prior test information and stable operating pressure.
Thermostats, sensors, limits, schedules, outputs and interlock.
Pump mode, mixing control and design-specific settings.
Cure confirmation, start date, staged temperatures and observations.
Approved changes, defects, restricted zones and remaining actions.
Owner handover
After commissioning
Let the controls operate normally and avoid several large changes together. Water underfloor heating can respond more slowly than radiators, especially in thick screed.
If a room does not reach temperature, check demand, actuator operation, flow and design conditions systematically rather than increasing every flowmeter or temperature.
Commissioning questions
Answers about filling, flow rates, temperature, zero readings and handover.
No. Filling and purging remove air and establish the water charge. Commissioning also proves pressure integrity, controls, heat-source demand, pump and mixing operation, balancing, first heat-up and handover records.
Use the design flow stated on the circuit schedule. A single generic flow rate is not appropriate because circuit lengths and room loads differ.
Use the designed water temperature and the limits for the screed and floor finish. Do not copy a setting from another project.
Possible causes include a closed valve or actuator, trapped air, incorrect pump operation, contamination or a control issue. Work through the system methodically and use a competent professional if the cause is unclear.
At minimum: layouts, test and commissioning records, circuit schedule, final settings, relevant certificates, product manuals and operating guidance.