Professional commissioning guide

How Do I Commission a Water Underfloor Heating System?

Commissioning proves that the system is filled, purged, leak-free, responding to its controls and delivering the design flow through every circuit.

It is more than connecting a hose to the manifold. Use the project design, current product instructions and heat-source requirements.

!
Competent-person work

Commissioning should be completed by a competent heating professional using the Uheat design, current product instructions and heat-source requirements. Electrical wiring and testing must be completed by a suitably qualified electrician.

Before commissioning begins

Confirm the installation is ready to test as a complete system

1

Design and labels

The manifold, loops and zone labels match the approved design and as-installed layout.

2

Pressure records

Required pressure tests were completed and recorded at the correct installation stages.

3

Cured floor layers

Screed, levellers, adhesives and finishes have cured or dried for the specified period.

4

Compatible equipment

The heat source, mixing control, pump, wiring centre, thermostats and actuators are installed.

5

Electrical checks

Protective devices and control wiring have been tested by the responsible electrician.

6

Design settings

Flow rates, circuit schedule and permitted temperature settings are available at the manifold.

Seven stages

Commissioning sequence

Work in order and record each result rather than adjusting the system by feel.

  1. 1
    Inspect and identify

    Check manifold orientation, valves, fill and drain points, vents, pump or mixing assembly, actuators and labels. Record approved site changes.

  2. 2
    Fill and purge each circuit

    Use the separate filling guide. Purge one circuit at a time until water runs without visible air, then restore the correct valve positions.

  3. 3
    Confirm pressure and leak integrity

    Set the cold pressure required by the design and heat-source instructions, inspect accessible joints and record the stable result.

  4. 4
    Prove controls and interlock

    Call for heat from each thermostat. Confirm the right actuator, pump and heat-source demand operate, then close correctly when demand ends.

  5. 5
    Set water temperature and pump

    Configure the heat source, mixing arrangement and pump to the design values. Confirm flow direction and investigate persistent air noise.

  6. 6
    Balance the circuits

    With the relevant zones open, adjust every flowmeter to its design rate. Recheck all loops after changes and record final flow.

  7. 7
    Complete the controlled first heat-up

    Follow the screed and finish start-up schedule, raise temperature gradually where instructed and prove every zone through a normal cycle.

!
Do not use underfloor heating to force-dry the floor

Starting too early or raising temperature too quickly can damage screed, adhesives or finishes. Cure, moisture and first-heat requirements come from the relevant material manufacturers.

Commissioning record

What to record

The handover should show what was designed, tested, set and changed.

Water underfloor heating commissioning records
RecordMinimum information
Project and systemAddress or area, heat source, manifold ID, commissioning date and responsible person.
Circuit scheduleZone or room, loop number, design flow, final measured flow and actuator channel.
TemperaturesRelevant flow, return, mixing and configured maximum values after stable operation.
PressureCold fill pressure, available test information and final stable operating pressure.
ControlsThermostat names, sensor or limit settings, schedules, wiring-centre outputs and interlock result.
Pump and mixingPump mode, mixing setting and any design-specific differential or bypass setting.
Floor start-upCure confirmation, start date, staged temperatures and observations.
ExceptionsApproved changes, unresolved defects, restricted zones and actions before handover.

Project and system

Area, heat source, manifold ID, date and responsible person.

Circuit schedule

Zone, loop, design and final flow, and actuator channel.

Temperatures

Flow, return, mixing and maximum values after stable operation.

Pressure

Cold fill, prior test information and stable operating pressure.

Controls

Thermostats, sensors, limits, schedules, outputs and interlock.

Pump and mixing

Pump mode, mixing control and design-specific settings.

Floor start-up

Cure confirmation, start date, staged temperatures and observations.

Exceptions

Approved changes, defects, restricted zones and remaining actions.

Owner handover

Leave a record that can be used after the installer leaves

  • As-built pipe layout and photographs taken before covering
  • Pressure-test and electrical test records and certificates
  • Manifold schedule, design flows and final settings
  • Heat-source, pump, mixing and control instructions
  • Approved floor-temperature limits and first heat-up record
  • Normal operation, seasonal start-up and fault contacts

After commissioning

Change one setting at a time

Let the controls operate normally and avoid several large changes together. Water underfloor heating can respond more slowly than radiators, especially in thick screed.

If a room does not reach temperature, check demand, actuator operation, flow and design conditions systematically rather than increasing every flowmeter or temperature.

Commissioning questions

Frequently Asked Questions

Answers about filling, flow rates, temperature, zero readings and handover.

Is filling the manifold the same as commissioning?

No. Filling and purging remove air and establish the water charge. Commissioning also proves pressure integrity, controls, heat-source demand, pump and mixing operation, balancing, first heat-up and handover records.

What flow rate should each loop have?

Use the design flow stated on the circuit schedule. A single generic flow rate is not appropriate because circuit lengths and room loads differ.

What temperature should I set?

Use the designed water temperature and the limits for the screed and floor finish. Do not copy a setting from another project.

Why is one flowmeter reading zero?

Possible causes include a closed valve or actuator, trapped air, incorrect pump operation, contamination or a control issue. Work through the system methodically and use a competent professional if the cause is unclear.

What should the homeowner receive?

At minimum: layouts, test and commissioning records, circuit schedule, final settings, relevant certificates, product manuals and operating guidance.

Commission to the project design

Need Help With the Manifold or Final Settings?

Use the current product instructions and circuit schedule. Speak to the Uheat technical team if the system arrangement or required values are unclear.