The UDry system is designed to be installed on joisted floors. This solution uses pipe clips or rail to fix the pipe into the insulation between the joists and pour a dry mix screed to cover the pipe. Please note: You need to make sure your joists can support 20kg per m2 for the dry screed.

Suitable Floor Constructions

  • Suspended Timber
  • Batten Floor

Suitable Floor Finishes

  • Tiles
  • Wood
  • Vinyl
  • Carpet

Notes

  • Insulation should be Rigid PIR.
  • Some insulation / screed combinations require a vapour barrier to be installed directly on the insulation before you install the pipe and lay the screed.
  • Your joists must be able to support 20kg per m2.
UDry

Tools Required

  • Pipe Cutter - Cut pipe to length
  • Pipe Reamer / Beveller - Prepare pipe for connection
  • Power Drill - Drill fixings for manifold
  • Spanner - Tighten pipe fixings
  • Hydraulic test Pump - Pressure test pipe loops